2 men and 5 boys together can finish a piece of work in 4 days, while 3 men and 6 boys can finish it in 3 days. Find the time taken: i) by one man alone to finish the work ii) by one boy alone to finish the work.

  • 0

One of the most important and conceptual question from linear equations in two variables in which we have given that 2 men and 5 boys together can finish a piece of work in 4 days, while 3 men and 6 boys can finish it in 3 days. We have to find the time taken:
i) by one man alone to finish the work
ii) by one boy alone to finish the work.

Kindly give me a detailed solution of this question

RS Aggarwal, Class 10, chapter 3E, question 37

Share

1 Answer

  1. Let the amount of work done by a Man alone in a day be M and by a Boy alone be B
    Given, 2 men and 5 boys together can finish a piece of work in 4 days
    Amount of work they can do in one day 2M+5B =1/4 — (1)
    Similarly, 3M+6B=1/3 — (2)
    Solving equations (1) and (2), we get B=1/36

    Substituting B in equation (2), we get M=1/18
    Hence, one man alone will take 18 days to do the work and one boy will take 36 days.

    • 0
Leave an answer

Leave an answer

Browse

Choose from here the video type.

Put Video ID here: https://www.youtube.com/watch?v=sdUUx5FdySs Ex: "sdUUx5FdySs".

Captcha Click on image to update the captcha.

Related Questions